Question

1 Approved Answer

Table 2. Previous Project Activity Description Activity Time Estimates (Weeks) Immediate Predecessors Optimistic Most Likely Pessimistic Requirements A 2 3 4 Market Assessment B 4

Table 2. Previous Project

Activity Description

Activity

Time Estimates (Weeks)

Immediate Predecessors

Optimistic

Most Likely

Pessimistic

Requirements

A

2

3

4

Market Assessment

B

4

7

10

A

Design

C

5

6

9

A

Development

D

6

7

16

C

Testing

E

7

9

10

D

Revising

F

4

5

6

B, E

Documentation

G

3

6

10

D

Quality

Assurance

H

2

4

7

C, E

Pricing

I

2

2

2

B

Installation

J

3

4

14

F, G, H, I

Project Handoff

K

2

3

4

J

Table 3. Crashing Data

Activity Designation

Crash Time

(Weeks)

Normal Cost ($)

Crash Cost ($)

A

3

10,000

10,000

B

6

20,000

25,000

C

5

15,000

30,000

D

6

45,000

65,000

E

8

10,000

20,000

F

4

15,000

18,000

G

4

20,000

30,000

H

3

10,000

15,000

I

2

5,000

5,000

J

5

40,000

50,000

K

2

15,000

25,000

Questions

1. Crash the project by three weeks. (Excel may prove useful for this question)

2. What is the duration of the project prior to crashing?

3. Which activities did you crash?

4. What is the additional cost to crash the project by three weeks?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_step_2

Step: 3

blur-text-image_step3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Finance questions