Table 7.12 Time (weeks) Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic ABCDEFGHIK 2 2 1 2 3 D,G 8 9 F,H 4
Table 7.12 Time (weeks) Activity Immediate Predecessor(s) Most Optimistic Most Likely Most Pessimistic ABCDEFGHIK 2 2 1 2 3 D,G 8 9 F,H 4 5 1 1 6720637706T 44274247 10 17 11 10 1 Using Table 7.12 if the project is due to be completed in 28 days, what is the probability that the project will be completed on or before the due date? Ogreater than 85% but less than or equal to 95% greater than 95% Ogreater than 75% but less than or equal to 85% Oless than or equal to 75%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To solve this problem we use the Program Evaluation and Review Technique PERT to analyze the given activities and their durations PERT is used to esti...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started