table [ [ Activity , Description,Optimistic ( a ) , Most Probable ( m ) , Pessimistic ( b ) ] , [ A

\table[[Activity,Description,Optimistic (a),Most Probable (m),Pessimistic (b)],[A,Plan event,2,3,4],[B,Select location,2.5,2,6],[C,Decide on speakers & vendors,4,4,4],[D,Prepare & mail brochures,2,4,6],[E,Update web site,1.5,2.5,3.5],[F,Final check with speakers & vendors,3.5,4,4.5],[G,Registration & hotel reservations,3,3,6],[H,Finalize last-minute details,2,5,5]]The Variance for Activity F is (round it up to 2 decimal places)
Group of answer choices
1.05
0.03
0.11
0.25
Suppose the Critical Path is A-C-D-G-H, the estimated probability that the project will be completed within 22 weeks is
Group of answer choices
49.84%
99.84%
50%
0.16%
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management in the supply chain decisions and cases

Authors: Roger G Schroeder, M. Johnny Rungtusanatham, Susan Meyer Goldstein

7th edition

77835433, 978-0077835439

More Books

Students also viewed these General Management questions

Question

Which kind of lens is used to make a magnifying glass?

Answered: 1 week ago