Question
1 Approved Answer
Tailoring your project management approach suggests that the appropriate project management processes, inputs, tools, techniques, outputs, and life cycle phases should be selected to manage
Tailoring your project management approach suggests that the appropriate project management processes, inputs, tools, techniques, outputs, and life cycle phases should be selected to manage a project. Tailoring should address the competing constraints of scope, schedule, cost, resources, quality, and risk. True or False