TDABC Bob Randall, cost accounting manager for Hemple Products, was asked to determine the costs of the activities performed within the company's Manufacturing Engineering Department.

TDABC

Bob Randall, cost accounting manager for Hemple Products, was asked to determine the costs of the activities performed within the company's Manufacturing Engineering Department. The department has the following activities: creating bills of materials (BOMs), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tools. The resource costs (from the general ledger) and the times to perform one unit of each activity are provided below.

Resource Costs Activities Unit Time Driver
Salaries $467,000 Creating BOMs 0.4 hr. No. of BOMs
Equipment 110,000 Designing tools 1.6 hrs. No. of tool designs
Supplies 43,000 Improving processes 0.9 hrs. Process improvement hrs.
Total $620,000 Training employees 1.9 hrs. No. of training sessions
Studying capabilities 1.9 hrs. Study hours

Total machine and labor hours (at practical capacity):

Machine hours 2,000
Engineering hours 18,000
Total hours 20,000

The activity, designing tools, uses the number of tools designed as the activity driver. Using a traditional approach, the cost of the designing tools activity was determined to be $186,000 with an expected activity output of 1,000 for the coming year. During the first week of the year, two jobs (Job 150 and Job 151) had a demand for 10 and 20 new tools, respectively.

Required:

1. Calculate the capacity cost rate for the Manufacturing Engineering Department. Round your answer to the nearest cent. $fill in the blank 1 per hour

2. Using the capacity cost rate, determine the activity rates for each activity. Round your answers to the nearest cent.

Activity Rates
Creating BOMs $fill in the blank 2 per BOM
Designing tools $fill in the blank 3 per tool design
Improving processes $fill in the blank 4 per process improvement hr.
Training employees $fill in the blank 5 per training session
Studying capabilities $fill in the blank 6 per study hour

3. Calculate the cost of designing tools that would be assigned to each job using the TDABC-derived activity rate and then repeat using the traditional ABC rate.

Job 150 Job 151
TDABC $fill in the blank 7 $fill in the blank 8
ABC $fill in the blank 9 $fill in the blank 10

4. Now suppose that time for creating BOMs is 0.4 for a standard product but that creating a BOM for a custom product adds an additional 0.2 hour. Express the time equation for this added complexity. Round your answers to two decimal places. Place the amounts left to right, lowest to highest.

BOM time = fill in the blank 11 + fill in the blank 12

Calculate the activity rate for the activity of creating a BOM for custom products. Round your answer to the nearest cent. $fill in the blank 13 per BOM

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Accounting

Authors: Frederick D. Choi, Gary K. Meek

6th edition

131588141, 978-0131588141

More Books

Students also viewed these Accounting questions

Question

and sat and sat

Answered: 1 week ago

Question

How do job descriptions and job specifications differ?

Answered: 1 week ago