Ten tasks with precedence and times have been identified to complete 60 units of Super RC Offroad Car in 8 hours. The summary of the
- Ten tasks with precedence and times have been identified to complete 60 units of Super RC Offroad Car in 8 hours. The summary of the information are as follows:
Task | Precedence | Time (min) | Task | Precedence | Time (min) |
A | - | 4 | F | D,E | 6 |
B | A | 3 | G | F | 4 |
C | - | 6 | H | F,G | 3 |
D | A,C | 7 | I | H | 8 |
E | B,D | 8 | J | I | 4 |
- Draw the relationship diagram.
(5 marks)
- Determine the minimum number of workstations.
(3 marks)
- Assign all the tasks into workstations.
(4 marks)
- Calculate the efficiency of the line.
(2 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started