Question

1 Approved Answer

Ten tasks with precedence and times have been identified to complete 60 units of Super RC Offroad Car in 8 hours. The summary of the

  1. Ten tasks with precedence and times have been identified to complete 60 units of Super RC Offroad Car in 8 hours. The summary of the information are as follows:

Task

Precedence

Time (min)

Task

Precedence

Time (min)

A

-

4

F

D,E

6

B

A

3

G

F

4

C

-

6

H

F,G

3

D

A,C

7

I

H

8

E

B,D

8

J

I

4

  1. Draw the relationship diagram.

(5 marks)

  1. Determine the minimum number of workstations.

(3 marks)

  1. Assign all the tasks into workstations.

(4 marks)

  1. Calculate the efficiency of the line.

(2 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management A Practical Introduction

Authors: Angelo Kinicki, Brian Williams

1st Edition

0078094054, 978-0078094057

More Books

Students also viewed these General Management questions