The actual cost of a material is $2.33 per produced unit. A Six sigma team develop a productivity project that reduce the cost to $2.20
The actual cost of a material is $2.33 per produced unit. A Six sigma team develop a productivity project that reduce the cost to $2.20 per produced unit. The total production is 15714 units in a year. The project required a new equipment with a cost of $4826. Without depreciation and learning curve, determine the IRR of the investment. Use two decimal points.
Step by Step Solution