Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The Basics of Capital Budgeting: IRR IRR A project's internal rate of return (IRR) is the -Select-compound ratediscount raterisk-free rateCorrect 1 of Item 1 that

The Basics of Capital Budgeting: IRR

IRR A project's internal rate of return (IRR) is the -Select-compound ratediscount raterisk-free rateCorrect 1 of Item 1 that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-YTMcoupongainCorrect 2 of Item 1 on a bond. The equation for calculating the IRR is:

CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must be a change in cash flow signs to calculate the IRR. The IRR equation is simply the NPV equation solved for the particular discount rate that causes NPV to equal -Select-IRRonezeroCorrect 3 of Item 1. The IRR calculation assumes that cash flows are reinvested at the -Select-IRRNPVWACCCorrect 4 of Item 1. If the IRR is -Select-lessgreaterCorrect 5 of Item 1 than the project's risk-adjusted cost of capital, then the project should be accepted; however, if the IRR is less than the project's risk-adjusted cost of capital, then the project should be -Select-acceptedrejectedCorrect 6 of Item 1. Because of the IRR reinvestment rate assumption, when -Select-mutually exclusiveindependentCorrect 7 of Item 1 projects are evaluated the IRR approach can lead to conflicting results from the NPV method. Two basic conditions can lead to conflicts between NPV and IRR: -Select-returntimingpreferenceCorrect 8 of Item 1 differences (earlier cash flows in one project vs. later cash flows in the other project) and project size (the cost of one project is larger than the other). When mutually exclusive projects are considered, then the -Select-IRRNPVCorrect 9 of Item 1 method should be used to evaluate projects. Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 9%.

0 1 2 3 4
Project A -1,000 650 320 270 390
Project B -1,000 250 255 420 840

What is Project As IRR? Do not round intermediate calculations. Round your answer to two decimal places. %

What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places. %

If the projects were independent, which project(s) would be accepted according to the IRR method? -Select-NeitherProject AProject BBoth projects A and BCorrect 1 of Item 3 If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? -Select-Neither Project AProject BBoth projects A and BCorrect 2 of Item 3 Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive? -Select-YesNoCorrect 3 of Item 3 The reason is -Select-the NPV and IRR approaches use the same reinvestment rate assumption so both approaches reach the same project acceptance when mutually projects are considered.the NPV and IRR approaches use different reinvestment rate assumptions so there can be a conflict in project acceptance when mutually exclusive projects are considered.Correct 4 of Item 3 Reinvestment at the -Select-IRRWACCCorrect 5 of Item 3 is the superior assumption, so when mutually exclusive projects are evaluated the -Select-NPVIRRCorrect 6 of Item 3 approach should be used for the capital budgeting decision.image text in transcribedimage text in transcribed

2. 2: The Basics of Capital Budgeting: NPV The Basics of Capital Budgeting: NPV NPV , and it is the best selection criterion. The -Select- the NPV, the more value the project adds; The net present value (NPV) method estimates how much a potential project will contribute to -Select and added value means a -Select- stock price. In equation form, the NPV is defined as: CFt is the expected cash flow at Time t, r is the project's risk-adjusted cost of capital, and N is its life, and cash outflows are treated as negative cash flows. The NPV calculation assumes that cash inflows can be reinvested at the project's risk-adjusted -Select-). When the firm is considering independent projects, if the project's NPV exceeds zero the firm should -Select the project. When the firm is considering mutually exclusive projects, the firm should accept the project with the -Select- NPV. Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 7%. 4 250 Project A Project B -1,150 - 1,150 600 200 360 295 200 350 700 What is Project A's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations. What is Project B's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations. If the projects were independent, which project(s) would be accepted? -Select- If the projects were mutually exclusive, which project(s) would be accepted? -Select- -Select- If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? -Select- Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive? -Select- The reason is -Select- Reinvestment at the -Select- is the superior assumption, so when mutually exclusive projects are evaluated the -Select- approach should be used for the capital budgeting decision. Save & Continue Continue without saving

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Personal Finance

Authors: Jeff Madura

5th edition

132994348, 978-0132994347

More Books

Students also viewed these Finance questions

Question

=+How does it affect the steady-state rate of growth?

Answered: 1 week ago