Question
The boxes on the network represent tasks where the top item in each box is the task name (i.e. A-1), the middle item is the
The boxes on the network represent tasks where the top item in each box is the task name (i.e. A-1), the middle item is the resource (i.e. Magenta), and the bottom item is the task duration in days. The task durations have already been cut by 50%.
a) Lay out the Critical Chain schedule for this project. You will first need to lay out the project network. You may use Microsoft Project, Excel, PowerPoint, or any other tool that allows you to draw the network. A hand drawn view of the project network for each step is okay if you dont have a tool you can easily use. Start the project on March 1, 2021. What is the project end date before leveling any resource conflicts? What is the project end date after leveling resources?
b) Identify the critical chain.
c) Lastly, size and insert the project and feeding buffers. Be sure to identify the approach you used for sizing the buffers. What is the project end date after inserting the appropriate buffers?
A-1 Magenta 5 days A-2 Black 10 days A-3 Green 15 days A-4 Red A-5 Magenta 20 days A-6 Red 10 days 15 days B-2 Magenta 10 days B-3 Blue 10 days B-4 Red 5 days Project Complete C-3 Blue 15 days C-4 Green 10 days C-5 Red 15 days C-6 Magenta 5 days D-3 Blue D-4 Green 20 days 5 days A-1 Magenta 5 days A-2 Black 10 days A-3 Green 15 days A-4 Red A-5 Magenta 20 days A-6 Red 10 days 15 days B-2 Magenta 10 days B-3 Blue 10 days B-4 Red 5 days Project Complete C-3 Blue 15 days C-4 Green 10 days C-5 Red 15 days C-6 Magenta 5 days D-3 Blue D-4 Green 20 days 5 daysStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started