The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $7,000 and has an expected life of 3 years. Annual project cash

The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $7,000 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions:

Project A Project B
Probability Cash Flows Probability Cash Flows
0.2 $6,750 0.2 $0
0.6 $7,000 0.6 $7,000
0.2 $7,250 0.2 $17,000

BPC has decided to evaluate the riskier project at 12% and the less-risky project at 9%. The data has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below.

Open spreadsheet

What is each project's expected annual cash flow? Round your answers to two decimal places.

Project A: $ fill in the blank 2

Project B: $ fill in the blank 3

Project B's standard deviation (B) is $5,425.86 and its coefficient of variation (CVB) is 0.71. What are the values of (A) and (CVA)? Round your answers to two decimal places.

A = $ fill in the blank 4

CVA = fill in the blank 5

Based on the risk-adjusted NPVs, which project should BPC choose?

Project AProject B

If you knew that Project B's cash flows were negatively correlated with the firm's other cash flow, but Project A's cash flows were positively correlated, how might this affect the decision?

This would make Project B more appealing.This would make Project B less appealing.

If Project B's cash flows were negatively correlated with gross domestic product (GDP), while A's cash flows were positively correlated, would that influence your risk assessment?

This would make Project B more appealing.This would make Project B less appealing.

image text in transcribed

the following probability distributions: questions below. Open spreadsheet a. What is each project's expected annual cash flow? Round your answers to two decimal places. Project A:$ Project B:$ A=$CVA= b. Based on the risk-adjusted NPVs, which project should BPC choose

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Routledge Handbook Of Responsible Investment

Authors: Tessa Hebb, James Hawley, Andreas Hoepner, Agnes Neher, David Wood

1st Edition

0415624517, 978-0415624510

More Books

Students also viewed these Finance questions