The chief surveyor of a firm that moves earth in preparation for the construction of roads has identified the activities and their durations for each
The chief surveyor of a firm that moves earth in preparation for the construction of roads has identified the
activities and their durations for each stage of an operation to prepare a difficult stretch of motorway as
shown in the following table. The surveyor needs to know how long the project will take and which are the
critical activities.
Road construction activities
Activity Duration days Preceding activity
A
B
C
D B
E B
F B
G AD
H AD
I F
J F
K CJ
L HEI,K
M CJ
i Using the information given in the table prepare a Gantt chart using Microsoft projects and
draw a network diagram.
ii What is the end date if the start date is October taking into consideration that Sundays
are nonworking days?
iii. What is the effect of B slipping by days?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started