The Church Brewery has determined the due dates and processing time for six customer orders that need to be processed (see table below). Job Processing
The Church Brewery has determined the due dates and processing time for six customer orders that need to be processed (see table below).
Job | Processing Time (days) | Due Date (days) |
A | 12 | 24 |
B | 3 | 8 |
C | 6 | 10 |
D | 10 | 32 |
E | 8 | 14 |
F | 4 | 14 |
A. Use the following priority rules to sequence the jobs:
i) Critical Ratio (CR), and ii) Minimum Slack Time (MST).
B. For each of the priority rules in part A, determine:
i) average flow time, and ii) average days late
C. (Which sequence would you recommend using? And Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started