Question
The company produces to order and never has any work-in-process inventories. The manufacturing facility uses a job costing system for product costing. Manufacturing overhead is
The company produces to order and never has any work-in-process inventories. The manufacturing facility uses a job costing system for product costing. Manufacturing overhead is applied to jobs based on direct labor cost. The cost analyst at 2M recently put together an estimate of overhead for the coming year, which is shown in the following table:
Category | Amount |
---|---|
Fabricating | $ 480,000 |
Machining | 960,000 |
Machine setup | 768,000 |
Shipping | 432,000 |
Certification | 240,000 |
Total | $ 2,880,000 |
The following are estimates for the three jobs planned for March:
Job MM03-11 | Job MM03-12 | Job MM03-13 | |
---|---|---|---|
Direct materials | $ 9,600 | $ 14,400 | $ 12,000 |
Direct labor | $ 24,000 | $ 38,400 | $ 31,200 |
Number of units | 300 | 750 | 600 |
Direct labor hours | 360 | 1,200 | 540 |
Machine-hours | 750 | 1,050 | 900 |
Setup-hours | 15 | 30 | 15 |
Certification required? | Yes | Yes | No |
2M is considering adopting an activity-based costing system. The cost analyst has studied the system and has recommended the following cost drivers for each of the overhead categories. The analyst has also estimated the annual volume for each of the cost drivers. This information follows.
Overhead Category | Cost Driver | Annual Cost Driver Volume | |
---|---|---|---|
Fabricating | Direct labor-hour | 24,000 | direct labor-hours |
Machining | Machine-hours | 30,000 | machine-hours |
Machine setup | Setups-hours | 1,200 | setup-hours |
Shipping | Units | 180,000 | units |
Certification | Certifications required | 20 | certifications required |
The average direct labor rate at 2M is $40 per hour.
A.What is the unit cost for each of the three jobs started and completed assuming 2M uses its current costing system?
Note: Round your answers to 2 decimal places.
B.What is the unit cost for each of the three jobs started and completed assuming 2M adopts the ABC system as designed by the cost analyst?
Note: Do not round intermediate calculations. Round your final answers to 2 decimal places
Unit cost
job MM02-11 | Job03-12 | Job MM03-13 | |
A. using the current costing system | |||
B. using the ABC system |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started