Question
1 Approved Answer
The critical path of a project Group of answer choices always has a negative slack. cannot change once the project has started. always has a
The critical path of a project
Group of answer choices
always has a negative slack.
cannot change once the project has started.
always has a positive slack.
is the longest path in the overall network diagram.
Step by Step Solution
There are 3 Steps involved in it
Step: 1