The demand for subassembly S is 120 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U.
The demand for subassembly S is 120 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
Construct a net material requirements plan using on-hand inventory (enter responses as whole numbers).
Week
| Lead Time
| ||||||||
Item
| 1
| 2
| 3
| 4
| 5
| 6
| 7
| (weeks)
| |
S
| Gross req
|
| 2 | ||||||
On hand
|
| ||||||||
Net req
|
| ||||||||
Order receipt
| |||||||||
Order release
|
|
T
| Gross req
| 1
| |||||||
On hand
| |||||||||
Net req
| |||||||||
Order receipt
| |||||||||
Order release
|
U
| Gross req
| 2
| |||||||
On hand
| |||||||||
Net req
| |||||||||
Order receipt
| |||||||||
Order release
|
|
V
| Gross req
| 2
| |||||||
On hand
| |||||||||
Net req
| |||||||||
Order receipt
| |||||||||
Order release
|
W
| Gross req
| 3 | |||||||
On hand
| |||||||||
Net req
| |||||||||
Order receipt
| |||||||||
Order release
|
X
| Gross req
| 1
| |||||||
On hand
| |||||||||
Net req
| |||||||||
Order receipt
| |||||||||
Order release
|
|
Y
| Gross req
| 2
| |||||||
On hand
| |||||||||
Net req
| |||||||||
Order receipt
| |||||||||
Order release
|
Part 9
Z
| Gross req
| 1
| |||||||
On hand
| |||||||||
Net req
| |||||||||
Order receipt
| |||||||||
Order release
|
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started