Question
The diagram below was developed for the project launch of Kitty Condo, a new product in the luxury cat cage market. Suppose that you are
The diagram below was developed for the project launch of Kitty Condo, a new product in the luxury cat cage market. Suppose that you are interested in finding ways to speed up the project at minimal additional cost. Determine the schedule for completing the project in
28
days at minimum cost. Penalty and project overhead costs are negligible. Time and cost data for each activity are shown below.
Normal | Crash | ||||
Activity | Time (days) | Cost ($) | Time (days) | Cost ($) | Diagram |
A | 6 | 1,300 | 4 | 2,900 | StartFinishACDFGIHEB |
B | 9 | 1,050 | 7 | 1,290 | |
C | 8 | 3,000 | 5 | 5,100 | |
D | 10 | 2,000 | 9 | 2,300 | |
E | 11 | 650 | 8 | 1,325 | |
F | 6 | 700 | 3 | 1,900 | |
G | 16 | 1,550 | 13 | 2,750 | |
H | 12 | 600 | 10 | 1,200 | |
I | 8 | 2,200 | 3 | 6,700 |
Fill in the table below to show the proper schedule for completing the project in
28
days at minimum cost (i.e., the activity times with crashing for each activity). (Enter your responses as whole numbers.)
Activity | Time according to schedule (days) | Activity | Time according to schedule (days) |
A |
| F |
|
B |
| G |
|
C |
| H |
|
D |
| I |
|
E |
|
Enter your answer in the edit fields and then click Check Answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started