The estimated times and immediate predecessors for the activities for Dale Jrs pit crew are given in the following table. Assume that the activity times

The estimated times and immediate predecessors for the activities for Dale Jrs pit crew are given in the following table. Assume that the activity times are independent. To solve this problem, calculate the expected completion time and variance for each activity, draw a network diagram, complete a forward and backward pass, and identify the critical path. Follow the step-by-step solution approach in Gray and Larson text, Chapter 7, Appendix 7.1 called PERT.

What is the probability that this path will be finished in 22 weeks or less?

Your answer should be carried out to two decimal places.

Activity

Immediate predecessor

Time (Weeks)

a

m

b

A

-

9

10

11

B

-

4

10

16

C

A

9

10

11

D

B

5

8

11

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Master The Art Of House Flipping

Authors: Livia V. Velez

1st Edition

979-8865806561

More Books

Students also viewed these Finance questions