The figures for the contingency and management reserves which are factored into the calculations of the project budget are derived from data, information, and calculations
The figures for the contingency and management reserves which are factored into the calculations of the project budget are derived from data, information, and calculations from a. The Resource Management Planning process b. The Cost Management Planning process c. The Schedule Management Planning process d. The Risk Management Planning process