The following are activities for developing and producing a Software system. draw a project network (30) compute (early & late) (start & finish) times for
The following are activities for developing and producing a
Software system.
- draw a project network (30)
- compute (early & late) (start & finish) times for each activity (25)
- determine slack (10)
- identify project duration (10)
- identify the critical path (25)
ID | Task Name | Duration | Finish-start Predecessors | Finish-start Lag | Additional Lag Relationships | Lag |
A | collect requirements | 2 wks | - | |||
B | analyze processes | 3 wks | A | |||
C | design processes | 6 wks | B | Start-Start task F | 3 wks | |
Finish-Finish task F | 1 wk | |||||
D | design screens | 1 wk | B | |||
E | design reports | 2 wks | B | |||
F | program | 4 wks | D, E | |||
G | test | 8 wks | F | |||
H | install | 2 wks | G |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started