The following data for a pottery company pertain to the production of 2,000 clay pots during July. Direct Materials (all materials purchased were used): Standard

The following data for a pottery company pertain to the production

of 2,000 clay pots during July.

Direct Materials (all materials purchased were used):

Standard cost: $2.00 per kilogram of clay

Total actual cost: $10,640

Standard cost allowed for units produced was $12,000

Materials quantity variance was $800 favourable

Direct Manufacturing Labour:

Standard cost is 2 pots per hour at $24.00 per hour

Actual cost per hour was $24.50

Actual labour was 1028 hours

show all steps!

a. What is the standard direct material amount per pot (in Kilograms)?

b. What is the materials price variance?

None of the other answers are correct

$1,040 favourable

$560 unfavourable

$800 unfavourable

$800 favourable

$560 favourable

c. What is the labour efficiency variance?

$500 unfavourable

$672 favourable

$672 unfavourable

None of the other answers are correct

$28 favourable

$500 favourable

d. What is the labour rate variance?

$486 favourable

$672 unfavourable

None of the other answers are correct

$186 favourable

$486 unfavourable

$514 favourable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

IT Audit In China

Authors: LIU Ruzhuo

1st Edition

981428145X, 978-9814281454

More Books

Students also viewed these Accounting questions

Question

Compare and contrast mobile wireless and fixed wireless.

Answered: 1 week ago