Question

1 Approved Answer

The following data is received from your contractor on a project's key component: Budgeted Cost of Work Performed (BCWP) = $100 Budgeted Cost of Work

The following data is received from your contractor on a project's key component: Budgeted Cost of Work Performed (BCWP) = $100 Budgeted Cost of Work Scheduled (BCWS) = $200 Actual Cost of Work Performed (ACWP) = $100 Budget at Completion (BAC) = $500 Latest Revised Estimate (LRE) = $900 Which of the following Earned Value Management (EVM) metrics can be determined from these data:
SPI = 0.5, CPI = 1.0, TCPI(BAC) = 1.0, TCPI(LRE) = 0.5
SPI = 0.5, CPI = 1.0, TCPI(BAC) = 2.0, TCPI(LRE) = 0.5
Schedule Performance Index (SPI) = 2.0, Cost Performance Index (CPI) = 1.0, To-Complete Performance Index [TCPI](BAC) = 2.0, TCPI(LRE) = 1.0
SPI = 2.0, CPI = 1.0, TCPI(BAC) = 1.0, TCPI(LRE) = 1.0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Markets and Institutions

Authors: Frederic S. Mishkin, Stanley G. Eakins

8th edition

013342362X, 978-0133423624

More Books

Students also viewed these Finance questions

Question

What is the IMF and what does it do?

Answered: 1 week ago

Question

Define line and staff authority

Answered: 1 week ago

Question

Define the process of communication

Answered: 1 week ago

Question

Explain the importance of effective communication

Answered: 1 week ago

Question

* What is the importance of soil testing in civil engineering?

Answered: 1 week ago

Question

Discuss data warehouse and give two examples

Answered: 1 week ago