The following data relate to direct materials costs for February: Materials cost per yard: standard, $2.00; actual. $2.10 Yards per unit: standard, 4.5 yards: actual,
The following data relate to direct materials costs for February: Materials cost per yard: standard, $2.00; actual. $2.10 Yards per unit: standard, 4.5 yards: actual, 4.75 yards Units of production: 9,500 The direct materials quantity variance is $4,512.50 unfavorable. $ $4,750.00 unfavorable. $ O $4,750.00 favorable. $4,512.50 favorable