The following data relates to a construction job started by Sparky Company during 2016: Total Contract Price $100,000 Actual costs incurred during 2016 20,000 Estimated

The following data relates to a construction job started by Sparky Company during 2016:

Total Contract Price

$100,000

Actual costs incurred during 2016

20,000

Estimated remaining costs

40,000

Billed to customer during 2016

30,000

Received from customer during 2016

10,000

Assuming that Sparky recognizes revenue over time according to percentage of completion, how much should Sparky recognize as gross profit for 2016?

A)

$33,333

B)

$26,667

C)

$13,333

D)

$0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Whispers In The Auditing Room

Authors: Azhar UL Haque

1st Edition

B0C63ZTK27, 979-8223789352

More Books

Students also viewed these Accounting questions

Question

3. Adapt to your reader's cul- tural background.

Answered: 1 week ago