[The following information applies to the questions displayed below.] Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct
[The following information applies to the questions displayed below.] |
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: |
Direct material: 5 pounds at $8.00 per pound | $ | 40.00 |
Direct labor: 2 hours at $14 per hour | 28.00 | |
Variable overhead: 2 hours at $5 per hour | 10.00 | |
Total standard variable cost per unit | $ | 78.00 |
The company also established the following cost formulas for its selling expenses: |
Fixed Cost per Month | Variable Cost per Unit Sold | |||||
Advertising | $ | 200,000 | ||||
Sales salaries and commissions | $ | 100,000 | $ | 12.00 | ||
Shipping expenses | $ | 3.00 | ||||
The planning budget for March was based on producing and selling 25,000 units. However, during March the company actually produced and sold 30,000 units and incurred the following costs: |
a. | Purchased 160,000 pounds of raw materials at a cost of $7.50 per pound. All of this material was used in production. |
b. | Direct-laborers worked 55,000 hours at a rate of $15.00 per hour. |
c. | Total variable manufacturing overhead for the month was $280,500. |
d. | Total advertising, sales salaries and commissions, and shipping expenses were $210,000, $455,000, and $115,000, respectively. |
1.
value: 5.00 points
Required information
Required: |
1. | What raw materials cost would be included in the companys flexible budget for March? |
References
eBook & Resources
WorksheetLearning Objective: 08-02 Prepare a report showing revenue and spending variances.Learning Objective: 08-06 Compute the variable manufacturing overhead rate and efficiency variances and explain their significance.
Difficulty: 2 MediumLearning Objective: 08-04 Compute the direct materials price and quantity variances and explain their significance.
Learning Objective: 08-01 Prepare a flexible budget.Learning Objective: 08-05 Compute the direct labor rate and efficiency variances and explain their significance.
Check my work
2.
value: 5.00 points
Required information
2. | What is the materials quantity variance for March? (Input the amount as a positive value. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).) |
References
eBook & Resources
WorksheetLearning Objective: 08-02 Prepare a report showing revenue and spending variances.Learning Objective: 08-06 Compute the variable manufacturing overhead rate and efficiency variances and explain their significance.
Difficulty: 2 MediumLearning Objective: 08-04 Compute the direct materials price and quantity variances and explain their significance.
Learning Objective: 08-01 Prepare a flexible budget.Learning Objective: 08-05 Compute the direct labor rate and efficiency variances and explain their significance.
Check my work
3.
value: 5.00 points
Required information
3. | What is the materials price variance for March? (Input the amount as a positive value. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).) |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started