Question

1 Approved Answer

The following is the time to complete an order for a manufactured product: Wait time from customer placing order to order being received by production:

The following is the time to complete an order for a manufactured product:

Wait time from customer placing order to order being received by production: 5 hours

Wait time from order received by production to machine set up for production: 1.5 hours

Inspection time: 0.5 hour

Process time: 2 hours

Move time: 1 hour

Which of the following is the manufacturing cycle efficiency for the order?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamental accounting principle

Authors: John J. Wild, Ken W. Shaw, Barbara Chiappetta

21st edition

1259119831, 9781259311703, 978-1259119835, 1259311708, 978-0078025587

More Books

Students also viewed these Accounting questions

Question

In what ways does agriculture contribute to economic growth?

Answered: 1 week ago