The following jobs need to be processed at J. J. Ruppers work center. Job Arrival Date Production Days Needed Due Date A 5 20 75
The following jobs need to be processed at J. J. Ruppers work center.
Job | Arrival Date | Production Days Needed | Due Date |
A | 5 | 20 | 75 |
B | 15 | 30 | 95 |
C | 17 | 16 | 70 |
D | 20 | 10 | 125 |
E | 25 | 18 | 105 |
In what sequence would the jobs be ranked according to the following rules: (a) FCFS, (b) SPT, (c) LPT, (d) EDD?