Question
1 Approved Answer
The following labor hours data have been collected for a nanotechnology project for periods 1 through 6 . Compute the SV , CV , SPI,
The following labor hours data have been collected for a nanotechnology project for periods through Compute the SV CV SPI, CPI, and PCIB for each period.SkippedSchodule informationDURBaseline budget needslabor hours Time periotTotal PV by periodDo not round intermediate calculations. Enter all values to decimal precision. For SPI, CPI, and PCIB enter in decimals ratherthan percentage format. de enter if the answer is