The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find

The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.

Activity Predecessor Duration (wks) Budget ($) Actual Cost ($) % Complete
a - 2 300 400 100
b - 3 200 180 100
c a 2 250 300 100
d a 5 600 400 20
e b,c 4 400 200 20

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Risk Sharing Finance

Authors: Bakkali Mirakhor, Saad Abbas

1st Edition

3110590468, 978-3110590463

More Books

Students also viewed these Finance questions

Question

6. Explain the strengths of a dialectical approach.

Answered: 1 week ago

Question

2. Discuss the types of messages that are communicated nonverbally.

Answered: 1 week ago