Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -
The following represents a project with four activities. All times are in weeks.
Activity | Immediate Predecessor | Optimistic Time | Most Likely Time | Pessimistic Time |
A | - | 6 | 10 | 14 |
B | - | 8 | 8 | 8 |
C | A | 6 | 9 | 18 |
D | B | 5 | 11 | 17 |
What is the minimum expected completion time for the project (please round off to two decimal digits)?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started