Question

1 Approved Answer

The following table details the tasks required for Indiana - based Frank Pianki Industries to manufacture a fully portable industrial vacuum cleaner. The times in

The following table details the tasks required for Indiana-based Frank Pianki Industries to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of 10 minutes.
Activity
Activity Description
Performance Time(mins)
Predecessors
A
Attach wheels to tub
4.0
B
Attach motor to lid
1.8
C
Attach battery pack
2.8
B
D
Attach safety cutoff
3.8
C
E
Attach filters
3.0
B
F
Attach lid to tub
2.0
A, E
G
Assemble attachments
3.2
H
Function test
3.5
D, F, G
I
Final inspection
2.0
H
J
Packing
2.0
I
Part 2
a-b) One of the possible assignment of tasks to workstations is shown correctly in
Fig. 2
.
Part 3
The efficiency of the assembly line with 3 workstations= enter your response here%(enter your response rounded to two decimal places).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Mind Management Not Time Management

Authors: David Kadavy

1st Edition

0578733692, 978-0578733692

More Books

Students also viewed these General Management questions

Question

47. If E[Y |X] = 1, show that Var(X Y ) Var(X)

Answered: 1 week ago

Question

What is the purpose of the staffing practice called Two-in-aBox?

Answered: 1 week ago

Question

What would you do?

Answered: 1 week ago