Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The following table lists the activities of a network along with their time estimates: Activity Predecessor (b) ABCDEFGHIY None None A ACDBEG E, F

 The following table lists the activities of a network along with their time estimates: Activity Predecessor   

The following table lists the activities of a network along with their time estimates: Activity Predecessor (b) ABCDEFGHIY None None A ACDBEG E, F H, I Optimistic (a) 3277WUNA 33 4 5 0 Duration (Days) Most Likely (m) 69751655 11 10 0 Pessimistic 15 27 16 8 17 15 14 54994 19 0 (a) Draw the project network. Use activity on node (A-O-N) method. (b) Identify the Critical Path. Calculate the length and variance of the Critical Path (c) Identify the non-critical activities. Work out the Total Slack (TS) and Free Slack (FS) for all the non-critical activities. (d) State whether the network is sensitive or insensitive! (e) What is the approximate probability that jobs on the critical path will be completed by the due date of (i) 35 days, (ii) 41 days? (0.50+0.50+0.50+0.50+3.00=5)

Step by Step Solution

3.29 Rating (149 Votes )

There are 3 Steps involved in it

Step: 1

Answer Lets tackle each part of the question a Draw the project network using the ActivityonNode AON method A3 C4 D2 E5 F3 HIJ2 G7 S8 HI0 b Identify t... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Business Analytics

Authors: Jeffrey Camm, James Cochran, Michael Fry, Jeffrey Ohlmann, David Anderson, Dennis Sweeney, Thomas Williams

1st Edition

128518727X, 978-1337360135, 978-1285187273

More Books

Students also viewed these General Management questions