The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. ItemLead TimeAmount on HandDirect ComponentsEnd20L(2),

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.

ItemLead TimeAmount

on HandDirect ComponentsEnd20L(2), C(1), K(3)L28B(2), J(3)C318G(2), B(2)K323H(4), B(2)B228J331G36H30

Click here for the Excel Data File

a.If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don't need to develop an MRP plan.)

b.An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Sport Management

Authors: Paul M. Pedersen, Lucie Thibault

6th Edition

1492550957, 978-1492550952

More Books

Students also viewed these General Management questions

Question

How do amplifiers differ from repeaters?

Answered: 1 week ago