The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 36 B 20 A C 25 B

The following tasks are to be performed on an assembly line:

TASK SECONDS TASKS THAT MUST PRECEDE
A 36
B 20 A
C 25 B
D 12 B
E 30 C
F 17 D
G 23 E, F
H 16 G

The workday is 7.7 hours long. The demand for completed product is 630 per day.

Find the cycle time required to meet the desired output rate.

Note: Round your answer to 1 decimal place.

What is the theoretical number of workstations required to meet the desired output rate?

Note: Round up your answer to the next whole number.

Balance the line using sequential restrictions and the longest-operating-time rule. Determine the task under each workstation and the idle time for each such task.

Note: Leave no cells blank - be certain to enter "0" wherever required. Round your answers to 1 decimal place.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Fundamentals

Authors: Robert N. Lussier

9th Edition

154438419X, 978-1544384191

More Books

Students also viewed these General Management questions

Question

What should the strategy of Edward Marshall Boehm be?

Answered: 1 week ago

Question

=+1. What was the independent variable in this study? Explain.

Answered: 1 week ago