The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 36 B 20 A C 25 B
The following tasks are to be performed on an assembly line:
TASK | SECONDS | TASKS THAT MUST PRECEDE |
---|---|---|
A | 36 | |
B | 20 | A |
C | 25 | B |
D | 12 | B |
E | 30 | C |
F | 17 | D |
G | 23 | E, F |
H | 16 | G |
The workday is 7.7 hours long. The demand for completed product is 630 per day.
Find the cycle time required to meet the desired output rate.
Note: Round your answer to 1 decimal place.
What is the theoretical number of workstations required to meet the desired output rate?
Note: Round up your answer to the next whole number.
Balance the line using sequential restrictions and the longest-operating-time rule. Determine the task under each workstation and the idle time for each such task.
Note: Leave no cells blank - be certain to enter "0" wherever required. Round your answers to 1 decimal place.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started