The forecasted mean daily demand for a product is 5210 units, the mean lead time is 8 days, and the standard deviation of forecast error
The forecasted mean daily demand for a product is 5210 units, the mean lead time is 8 days, and the standard deviation of forecast error during lead time is 1235 units. What is the service level for this product when the reorder point is 45130 units?
2.79% | ||
77.94% | ||
99.74% | ||
None of the above |
2 points
QUESTION 51
A product has a mean demand of 50 with a standard deviation of 4. If the retailer wants to maintain a 99% customer service, how many units will they need to keep in stock?
54 | ||
59 | ||
98 | ||
62 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started