Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on July 3, 2017, and be

The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on July 3, 2017, and be completed in time for the start of the 2020 season. A penalty clause of $250,000 per day of delay beyond April 3 is written into the contract. Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project. He also said if they were successful, the prospects of future projects are bright since there is a projected renaissance in building classic ball parks with modern luxury boxes.

ASSIGNMENT Given the information provided in Table 6.3, construct a network schedule for the stadium project and answer the following questions:

1. Will the project be able to be completed by the April 3 deadline? How long will it take?

2. What is the critical path for the project?

3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule.

Chapter 6 Developing a Project Plan 205 TABLE 6.3 Shoreline Stadium Case ID

Activity Duration Predecessor(s)

1 Baseball Stadium

2 Clear stadium site 70 days

3 Demolish building 30 days 2 4

Set up construction site 70 days 3 5

Drive support piling 120 days 4 6

Pour lower concrete bowl 120 days 5 7

Pour main concourse 120 days

6 8 Install playing field 90 days 6 9

Construct upper steel bowl 120 days 6 10

Install seats 140 days 9 11

Build luxury boxes 90 days 9 12

Install jumbotron 30 days 9 13

Stadium infrastructure 120 days 9 14

Construct steel canopy 75 days 10 15

Light installation 30 days 10 16

Build roof supports 90 days 4 17

Construct roof 180 days 16 18

Install roof tracks 90 days 14 19

Install roof 90 days 17, 18 20

Inspection 20 days 8, 11, 13, 15, 19

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Brand Management

Authors: Alexander Chernev

3rd Edition

193657263X, 9781936572632

More Books

Students also viewed these General Management questions