The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The companys cost analyst has concluded that utilities cost is
The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The companys cost analyst has concluded that utilities cost is a mixed cost, and he is attempting to find a base that correlates with the cost. The controller has suggested that tons mined might be a good base to use in developing a cost formula. The production superintendent disagrees; she thinks that direct labor-hours would be a better base. The cost analyst has decided to try both bases and has assembled the following information:
Quarter Tons Mined Direct Labor-Hours Utilities Cost Year 1: First 34,000 6,900 $ 69,000 Second 21,000 4,900 $ 64,000 Third 39,000 5,900 $ 79,000 Fourth 31,000 7,900 $ 94,000 Year 2: First 37,000 13,800 $ 119,000 Second 44,000 14,700 $ 124,000 Third 49,000 11,800 $ 104,000 Fourth 47,000 14,800 $ 139,000
Garrison 17e Required:
1-a. Using tons mined as the independent variable, prepare a scattergraph that plots tons mined on the horizontal axis and utilities cost on the vertical axis.
Instructions: 1. On the graph below, use the point tool (Year 1-1st quarter) to plot tons mined on the horizontal axis and utilities cost on the Vertical axis. 2. Repeat the same process for the plotter tools (Year 1-2nd quarter to Year 2-4th quarter). 3. To enter exact coordinates, click on the point and enter the values of x and y. 4. To remove a point from the graph, click on the point and select delete option.
1-b. Using the least-squares regression method, estimate the variable utilities cost per ton mined and the total fixed utilities cost per quarter. Express these estimates in the form Y = a + bX. (Round the Variable cost per unit to 2 decimal places and Fixed Cost to the nearest whole dollar amount.)
2-a. Using direct labor-hours as the independent variable, prepare a scattergraph that plots direct labor-hours on the horizontal axis and utilities cost on the vertical axis.
Instructions: 1. On the graph below, use the point tool (Year 1-1st quarter) to plot direct labor-hours on the horizontal axis and utilities cost on the Vertical axis. 2. Repeat the same process for the plotter tools (Year 1-2nd quarter to Year 2-4th quarter). 3. To enter exact coordinates, click on the point and enter the values of x and y. 4. To remove a point from the graph, click on the point and select delete option.
2-b. Using the least-squares regression method, estimate the variable utilities cost per direct labor-hour and the total fixed utilities cost per quarter. Express these estimates in the form Y = a + bX. (Round the Variable cost to 2 decimal places and Fixed Cost to the nearest whole dollar amount.)
3. Would you recommend that the company use tons mined or direct labor-hours as a base for planning utilities cost?
The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The companys cost analyst has concluded that utilities cost is a mixed cost, and he is attempting to find a base that correlates with the cost. The controller has suggested that tons mined might be a good base to use in developing a cost formula. The production superintendent disagrees; she thinks that direct labor-hours would be a better base. The cost analyst has decided to try both bases and has assembled the following information:
Quarter | Tons Mined | Direct Labor-Hours | Utilities Cost | |||
Year 1: | ||||||
First | 34,000 | 6,900 | $ | 69,000 | ||
Second | 21,000 | 4,900 | $ | 64,000 | ||
Third | 39,000 | 5,900 | $ | 79,000 | ||
Fourth | 31,000 | 7,900 | $ | 94,000 | ||
Year 2: | ||||||
First | 37,000 | 13,800 | $ | 119,000 | ||
Second | 44,000 | 14,700 | $ | 124,000 | ||
Third | 49,000 | 11,800 | $ | 104,000 | ||
Fourth | 47,000 | 14,800 | $ | 139,000 | ||
Garrison 17e Required:
1-a. Using tons mined as the independent variable, prepare a scattergraph that plots tons mined on the horizontal axis and utilities cost on the vertical axis.
Instructions: 1. On the graph below, use the point tool (Year 1-1st quarter) to plot tons mined on the horizontal axis and utilities cost on the Vertical axis. 2. Repeat the same process for the plotter tools (Year 1-2nd quarter to Year 2-4th quarter). 3. To enter exact coordinates, click on the point and enter the values of x and y. 4. To remove a point from the graph, click on the point and select delete option.
1-b. Using the least-squares regression method, estimate the variable utilities cost per ton mined and the total fixed utilities cost per quarter. Express these estimates in the form Y = a + bX. (Round the Variable cost per unit to 2 decimal places and Fixed Cost to the nearest whole dollar amount.)
2-a. Using direct labor-hours as the independent variable, prepare a scattergraph that plots direct labor-hours on the horizontal axis and utilities cost on the vertical axis.
Instructions: 1. On the graph below, use the point tool (Year 1-1st quarter) to plot direct labor-hours on the horizontal axis and utilities cost on the Vertical axis. 2. Repeat the same process for the plotter tools (Year 1-2nd quarter to Year 2-4th quarter). 3. To enter exact coordinates, click on the point and enter the values of x and y. 4. To remove a point from the graph, click on the point and select delete option.
2-b. Using the least-squares regression method, estimate the variable utilities cost per direct labor-hour and the total fixed utilities cost per quarter. Express these estimates in the form Y = a + bX. (Round the Variable cost to 2 decimal places and Fixed Cost to the nearest whole dollar amount.)
3. Would you recommend that the company use tons mined or direct labor-hours as a base for planning utilities cost?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started