Question
The land you are planning to buy for the brewery is for sale for $100,000. You are planning on contracting out the parts of the
The land you are planning to buy for the brewery is for sale for $100,000. You are planning on contracting out the parts of the job yourself. From the various specialties you receive the following cost ranges:
Specialty | Optimistic Cost | Most Likely Cost | Pessimistic Cost |
Site Preparation & Foundation | $15000 | 22500 | 31000 |
Structure | 400000 | 525000 | 600000 |
Utilities | 30000 | 37000 | 40000 |
Equipment Install | 150000 | 200000 | 275000 |
Finishing | 50000 | 70000 | 100000 |
Using three-point estimation, determine the cost estimate to build the brewery.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To determine the cost estimate to build the brewery using threepoint estimation you can use the PERT ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Advanced Accounting
Authors: Gail Fayerman
1st Canadian Edition
9781118774113, 1118774116, 111803791X, 978-1118037911
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App