The manager of Champion Cooling Company has recently implemented a statistical process control method. The accompanying table shows the recorded temperatures of five different samples

The manager of Champion Cooling Company has recently implemented a statistical process control method. The accompanying table shows the recorded temperatures of five different samples of walk-in coolers that were produced in the previous month.
Sample 1 Sample 2 Sample 3 Sample 4 Sample 5
Unit 1102100.1101.1102102.7
Unit 2105.9104.4100.4105.9103.7
Unit 3101.8103.2103.5104106.1
Unit 4105.6101.2101102.1102.5
Unit 5100.6100.7104.9107102
sing the data in the table above, the upper control limit for the x-bar chart with three sigma limits is:
Question 41 options:
A)
103.2.
B)
105.7.
C)
102.3.
D)
104.7.
Question 42(3 points)
Saved
Using the data in the table above, the center line of the R-chart is:
Question 42 options:
A)
4.6.
B)
3.9.
C)
4.4.
D)
5.3.
Question 43(3 points)
If an x-bar chart is constructed using the data in the table above, what conclusion can be reached?
Question 43 options:
A)
The process is capable.
B)
The process is both capable and in control.
C)
The process is out of control.
D)
The process is in control.
Question 39(3 points)
Saved
Using the data in the table above, what is the value of the center line for the chart that monitors performance to target?
Question 39 options:
A)
3.9
B)
103.7
C)
103.0
D)
102.2
Question 40(3 points)
Saved
Using the data in the table above, the first point plotted on the x-bar chart has a value of:
Question 40 options:
A)
102.0.
B)
103.7.
C)
103.2.
D)
104.3.
Question 41(3 points)
Using the data in the table above, the upper control limit for the x-bar chart with three sigma limits is:
Question 41 options:
A)
103.2.
B)
105.7.
C)
102.3.
D)
104.7.
Question 42(3 points)
Saved
Using the data in the table above, the center line of the R-chart is:
Question 42 options:
A)
4.6.
B)
3.9.
C)
4.4.
D)
5.3.
Question 43(3 points)
If an x-bar chart is constructed using the data in the table above, what conclusion can be reached?
Question 43 options:
A)
The process is capable.
B)
The process is both capable and in control.
C)
The process is out of control.
D)
The process is in control.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of strategic management

Authors: Charles w. l. hill, Gareth r. Jones

3rd Edition

1111525196, 978-1111525194

More Books

Students also viewed these General Management questions