Question
The managing partner of the Scott Corey account-ing firm (see Problem 11-34) has decided that the system must be up and running in 16 weeks.
The managing partner of the Scott Corey account-ing firm (see Problem 11-34) has decided that the system must be up and running in 16 weeks. Con-sequently, information about crashing the project was put together and is shown in the following table:
ACTIVITY IMMEDIATE PREDECESSORS A B C D E F G H A B A C D, E F, G NORMAL TIME (WEEKS) 3 4 6 2 5 2 4 5 CRASH TIME (WEEKS) 2 3 4 1 3 1 2 3 NORMAL COST ($) 8,000 9,000 CRASH COST ($) 9,800 10,000 12,000 15,000 15,000 15,500 5,000 7,500 8,000 5,000 8,700 9,000 9,400 6,600
(a) If the project is to be finished in 16 weeks, which activity or activities should be crashed to do this at the least additional cost? What is the
(b) List all the paths in this network. After the crashing in part (a) has been done, what is the time required for each path? If the proj-ect completion time must be reduced another week so that the total time is 15 weeks, which activity or activities should be crashed? Solve this by inspection. Note that it is sometimes better to crash an activity that is not the least cost for crashing if it is on several paths rather than to crash several activities on separate paths when there is more than one critical path.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started