The MindGineer Project for your organization has been assigned to you to oversee as the project manager. A completion budget of RM 1,500,000 and a
The MindGineer Project for your organization has been assigned to you to oversee as the project manager. A completion budget of RM 1,500,000 and a 18-month timeline are set forth for this project. The project has been ongoing for some time, and it is currently 30% finished, even though you were expected to guarantee 35% completion at this point. Your project continued to be delayed and has already cost RM 485,230 as a result of the