The numbers left are confirmed correct. The product development group at Landon Corporation has been working on a new computer software product that has the

The numbers left are confirmed correct.
The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources, Landon's management learned that a competitor is working to introduce a similar product. As a result, Landon's top management increased its pressure on the product development group. The group's leader turned to PERT/CPM as an aid to scheduling the activities remaining before the new product can be brought to the market. The project network is as follows:
The activity time estimates (in weeks) are as follows:
Activity Optimistic Most Probable Pessimistic
A 2.03.04.0
B 2.03.58.0
C 4.09.014.0
D 4.06.014.0
E 3.04.05.0
F 1.03.05.0
G 7.08.513.0
H 5.56.06.5
I 2.06.010.0
J 2.02.56.0
Develop an activity schedule for this project and identify the critical path activities.
If required, round your answers to two decimal places. If your answer is zero enter 0.
Activity Expected Time Variance
A fill in the blank 1
3.00
fill in the blank 2
0.11
B fill in the blank 3
fill in the blank 4
C fill in the blank 5
fill in the blank 6
D fill in the blank 7
fill in the blank 8
E fill in the blank 9
4.00
fill in the blank 10
F fill in the blank 11
fill in the blank 12
G fill in the blank 13
fill in the blank 14
H fill in the blank 15
fill in the blank 16
I fill in the blank 17
6.00
fill in the blank 18
J fill in the blank 19
fill in the blank 20
Earliest Latest Earliest Latest Critical
Activity Start Start Finish Finish Slack Activity
A fill in the blank 21
0
fill in the blank 22
fill in the blank 23
fill in the blank 24
fill in the blank 25
No
B fill in the blank 27
fill in the blank 28
fill in the blank 29
fill in the blank 30
fill in the blank 31
0
Yes
C fill in the blank 33
fill in the blank 34
fill in the blank 35
fill in the blank 36
fill in the blank 37
0
Yes
D fill in the blank 39
fill in the blank 40
fill in the blank 41
fill in the blank 42
fill in the blank 43
Yes
E fill in the blank 45
fill in the blank 46
7.00
fill in the blank 47
fill in the blank 48
fill in the blank 49
No
F fill in the blank 51
fill in the blank 52
fill in the blank 53
fill in the blank 54
fill in the blank 55
0
No
G fill in the blank 57
fill in the blank 58
fill in the blank 59
fill in the blank 60
fill in the blank 61
0
No
H fill in the blank 63
fill in the blank 64
fill in the blank 65
fill in the blank 66
fill in the blank 67
0
Yes
I fill in the blank 69
fill in the blank 70
fill in the blank 71
fill in the blank 72
fill in the blank 73
0
Yes
J fill in the blank 75
fill in the blank 76
fill in the blank 77
fill in the blank 78
fill in the blank 79
13.00
No
Critical Path:
B-F-J
What is the probability that the project will be completed so that Landon Corporation may introduce the new product within 25 weeks? Within 30 weeks?
Expected project completion time = fill in the blank 82
weeks. If required, round your answer to two decimal places.
fill in the blank 83
. If required, round your answer to two decimal places.
P(25 weeks)= fill in the blank 84
. If required, round your answer to four decimal places.
P(30 weeks)= fill in the blank 85
. If required, round your answer to four decimal places.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: R. Dan Reid, Nada R. Sanders

4th edition

9780470556702, 470325046, 470556706, 978-0470325049

More Books

Students also viewed these General Management questions