The numbers left are confirmed correct. The product development group at Landon Corporation has been working on a new computer software product that has the
The numbers left are confirmed correct.
The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources, Landon's management learned that a competitor is working to introduce a similar product. As a result, Landon's top management increased its pressure on the product development group. The group's leader turned to PERTCPM as an aid to scheduling the activities remaining before the new product can be brought to the market. The project network is as follows:
The activity time estimates in weeks are as follows:
Activity Optimistic Most Probable Pessimistic
A
B
C
D
E
F
G
H
I
J
Develop an activity schedule for this project and identify the critical path activities.
If required, round your answers to two decimal places. If your answer is zero enter
Activity Expected Time Variance
A fill in the blank
fill in the blank
B fill in the blank
fill in the blank
C fill in the blank
fill in the blank
D fill in the blank
fill in the blank
E fill in the blank
fill in the blank
F fill in the blank
fill in the blank
G fill in the blank
fill in the blank
H fill in the blank
fill in the blank
I fill in the blank
fill in the blank
J fill in the blank
fill in the blank
Earliest Latest Earliest Latest Critical
Activity Start Start Finish Finish Slack Activity
A fill in the blank
fill in the blank
fill in the blank
fill in the blank
fill in the blank
No
B fill in the blank
fill in the blank
fill in the blank
fill in the blank
fill in the blank
Yes
C fill in the blank
fill in the blank
fill in the blank
fill in the blank
fill in the blank
Yes
D fill in the blank
fill in the blank
fill in the blank
fill in the blank
fill in the blank
Yes
E fill in the blank
fill in the blank
fill in the blank
fill in the blank
fill in the blank
No
F fill in the blank
fill in the blank
fill in the blank
fill in the blank
fill in the blank
No
G fill in the blank
fill in the blank
fill in the blank
fill in the blank
fill in the blank
No
H fill in the blank
fill in the blank
fill in the blank
fill in the blank
fill in the blank
Yes
I fill in the blank
fill in the blank
fill in the blank
fill in the blank
fill in the blank
Yes
J fill in the blank
fill in the blank
fill in the blank
fill in the blank
fill in the blank
No
Critical Path:
BFJ
What is the probability that the project will be completed so that Landon Corporation may introduce the new product within weeks? Within weeks?
Expected project completion time fill in the blank
weeks. If required, round your answer to two decimal places.
fill in the blank
If required, round your answer to two decimal places.
P weeks fill in the blank
If required, round your answer to four decimal places.
P weeks fill in the blank
If required, round your answer to four decimal places.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started