The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time (makespan)

The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time (makespan) to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:

 

Car
Body Work (Hours)
Paint (Hours)
A
8
7
B
9
4
C
7
9
D
3
4
E
12
5

  

How much time, in hours, is needed to complete all the five jobs (refer to the Johnson's rule and the Gantt diagram)?

Step by Step Solution

3.48 Rating (165 Votes )

There are 3 Steps involved in it

Step: 1

Using the Johnson s Rule the total time needed to complete the five jobs is 27 hours This is determi... blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Data Analysis And Decision Making

Authors: Christian Albright, Wayne Winston, Christopher Zappe

4th Edition

538476125, 978-0538476126

More Books

Students explore these related Business Communication questions