The precedenece diagram. answers below QUESTION 2 Calculate the precedence diagram given below and answer the following questions: 1. The earliest start date of Activity
The precedenece diagram. answers below
QUESTION 2 Calculate the precedence diagram given below and answer the following questions: 1. The earliest start date of Activity K is days 2. The free float of Activity H is days 3. The total float of Activity A is days 4. The latest finish date of Activity F is Day A D 4 5 K B E G 6 2 Start L End 6 F H (Note: the number under each box represents the duration of the activity) (Unit of duration: days)Step by Step Solution