The project manager is reconciling the expense plan with any funding limits imposed by the approved budget. What process is this? a. Integrated Change control
- The project manager is reconciling the expense plan with any funding limits imposed by the approved budget. What process is this?
a. Integrated Change control
b. Determine budget
c. Control cost
d. Estimate costs
2. In order to calculate the estimate at completion (EAC), the following is typically needed:
a. Actual Cost and the estimate to complete the unfinished work
b. Earned Value and the actual cost
3. Earned value of a project is $127,200 and the planned value is $143,000. How will you explain this project performance?
a. Ahead of schedule
b. Behind schedule
c. On schedule
d. Cannot say anything
4. A stakeholder on a project has asked for a change to the project that has an impact on the project budget. To implement the change------- has to be followed.
a. Change control Board
b. Changes cost estimate
c. Cost performance baseline
d. Monitoring and controlling group
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started