Question

1 Approved Answer

The project manager is reconciling the expense plan with any funding limits imposed by the approved budget. What process is this? a. Integrated Change control

  1. The project manager is reconciling the expense plan with any funding limits imposed by the approved budget. What process is this?

a. Integrated Change control

b. Determine budget

c. Control cost

d. Estimate costs

2. In order to calculate the estimate at completion (EAC), the following is typically needed:

a. Actual Cost and the estimate to complete the unfinished work

b. Earned Value and the actual cost

3. Earned value of a project is $127,200 and the planned value is $143,000. How will you explain this project performance?

a. Ahead of schedule

b. Behind schedule

c. On schedule

d. Cannot say anything

4. A stakeholder on a project has asked for a change to the project that has an impact on the project budget. To implement the change------- has to be followed.

a. Change control Board

b. Changes cost estimate

c. Cost performance baseline

d. Monitoring and controlling group

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Small Business Management Launching & Growing Entrepreneurial Ventures

Authors: Justin Longenecker, William Petty, Leslie Palich, Frank Hoy

17th edition

9781285972565, 1133947751, 1285972562, 978-1133947752

More Books

Students also viewed these General Management questions