The project manager is reviewing the current earned value report, which shows the following: Schedule Performance Index (SPI) = 1.2 Cost Performance Index (CPI) =
The project manager is reviewing the current earned value report, which shows the following: Schedule Performance Index (SPI) = 1.2 Cost Performance Index (CPI) = 1.6 Planned Value (PV) = $200,000 Schedule Variance (SV) = $40,000 What is the project's Cost Variance (CV)? a. $160,000 b. $125,000 c. $90,000 d. $96,000