The Speedy Pizza Palace is revamping its order-processing and pizza-making procedures. In order to deliver fresh pizza fast, six elements must be completed. The management
The Speedy Pizza Palace is revamping its order-processing and pizza-making
procedures. In order to deliver fresh pizza fast, six elements must be completed.
The management of Speedy Pizza expects an efficiency of 90%.
Activity | Description | Precedence | Time (min) |
A | Receive order | - | 2 |
B | Shape dough | A | 1 |
C | Prepare toppings | A | 2 |
D | Assemble pizza | B, C | 3 |
E | Bake pizza | D | 3 |
F | Deliver pizza | E | 3 |
- Construct a precedence diagram for the process. ( 3 marks )
- Compute the desired cycle time given that the demand of pizza is 120 per night (5:00 pm to 1:00 am). ( 3 marks )
- What is the theoretical number of workstations? ( 4 marks )
- Balance the line. ( 8 marks )
- Comment on the answer in (d). ( 2 marks )
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started