Question

1 Approved Answer

The standard cost card for one unit of a product shows the following costs for Material and Labour. Material 4 pieces @ Rs.5.00 Labour 10

The standard cost card for one unit of a product shows the following costs for Material and Labour.

Material 4 pieces @ Rs.5.00

Labour 10 hours @ Rs.1.50

5,700 units of the product were manufactured during the month of March 2003 with the following materials and labour costs:

Material 23,000 pieces @ Rs. 4.95

Labour 56,800 hours @ Rs.1.52

Calculate appropriate Material and Labour variances.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Applying IFRS Standards

Authors: Ruth Picker, Kerry Clark, John Dunn, David Kolitz, Gilad Livne, Jance Loftus, Leo Van Der Tas

4th Edition

1119159229, 9781119159223

More Books

Students also viewed these Accounting questions