The successor activity starts 1 0 days before the predecessor activity ends. This 1 0 days is called: Question 3 0 options: Lag Lead Crash

The successor activity starts 10 days before the predecessor activity ends. This 10 days is called:
Question 30 options:
Lag
Lead
Crash
Sunk