The table below contains information about an environmental clean - up project in the township of Hiles. Shorten the project three weeks by finding the

The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.
\table[[Activity,\table[[Normal Time],[(weeks)]],\table[[Crash Time],[(weeks)]],\table[[Cost to Crash],[($ per week)]],Immediate Predecessor(s)],[A,8,7,200,None],[B,11,10,150,None],[C,5,3,200,A],[D,4,2,200,A],[E,1,1,-,B],[F,2,2,-,C, D],[G,5,3,150,D, E],[H,4,3,150,F],[I,2,2,-,G]]
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.)
\table[[Activity,\table[[Time according to],[schedule (weeks)]],Activity,\table[[Time according to],[schedule (weeks)]]],[A,,F,],[B,,G,],[C,,H,],[D,,I,],[E,,,]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Stephen P Robbins, Mary Coulter

11th Edition

9780273752776, 132163845, 273752774, 978-0132163842

More Books

Students also viewed these General Management questions

Question

1. Calculate and report the range of this distribution.

Answered: 1 week ago