Question
1 Approved Answer
The total completion time of a project is expected to be 2 2 days. Task A is planned to take six days. Task B is
The total completion time of a project is expected to be days. Task A is planned to take six days. Task B is planned to take five days. Task C is planned to take seven days. The tasks have a serial or sequential relationship. Task A takes eight days to be completed instead of six days. How much slack does the project have now that Task A is finished?
Question options:
Positive days slack.
Positive days slack.
Positive days slack.
Negative days slack.